SLURRY SEAL WORK STARTS THIS WEEK

August 22, 2022 3:20 a.m.

Slurry seal work starts this week on a number of streets in the City of Roseburg.

A City release said the maintenance will extend the life of just over two miles of streets.

Vehicle owners must remove their vehicles from street sections scheduled and posted for maintenance to allow crews to complete the work.

The Public Works Department has hired contractors to apply the slurry seals to sections of streets between Thursday and Saturday. Each section should be completed the same day.

The release said slurry seals combine a thin layer of aggregate with an asphalt emulsifier, that is applied to a paved surface to preserve and protect the underlying pavement structure and provide a new, smooth driving surface.

“No parking” and “road closed” signs will be set out three days before each closure. Roads in neighborhoods accessible from Parker Road south of Newton Creek Road will have limited access on Friday. Parking will only be available on Newton Creek Road for up to eight hours that day, while nearby streets are slurry sealed.

All the roads in the work areas will be slurry sealed in one day to minimize disruption to residents. All service providers have been notified and given road maintenance schedules so they can work around the maintenance schedule.

Residents who normally park their vehicles on streets scheduled for maintenance must remove those vehicles before work starts so crews can apply the slurry seals. Any vehicles found on those streets after the scheduled start date will be towed at the owner’s expense.

Work will take place in several sections of Roseburg. The full schedule with the specific streets is posted with this story at www.541radio.com

Thursday, Aug. 25, 2022 (tentative, weather permitting)

 NW Calkins Avenue: From NW Troost Street to NW El Dorado Street

 W Keady Court: From W Harvard Avenue to end of street

 W Bertha Avenue: From W Stanton Street to W Elaine Avenue

 W Elaine Avenue: From W Stanton Street to W Bertha Avenue

 W Alpha Street: From W Fair Street to end of street

 

Friday, Aug. 26, 2022 (tentative, weather permitting)

 NW Calkins Avenue: From NW El Dorado Street to NW Keasey Street

 NE Parker Road: From NE Newton Creek Road to end of street

 NE Peggy Avenue: From NE Parker Road to end of street

 Dobie Court: From Kirby Avenue to end of street

 Kirby Avenue: From NE Parker Road to end of street

 NE Carmen Street: From Kirby Avenue to end of street

 

Saturday, Aug. 27, 2022 (tentative, weather permitting)

 NW Kline Street: From NW Valley View Drive to NW Moore Avenue

 NW Kline Street: From NW Garden Valley Boulevard to NW Valley View Drive

 W Stanton Street: From W Harvard Avenue to 450 feet south of W Bertha Avenue